Welcome to Weidong Machines
Tub grinder capacity for biomass fuel: buyers should define representative feed lots, accepted product, total elapsed time and the complete work cell before comparing capacity claims.
biomass fuel can include woody branches, bark-rich bulking material, clean pallets, fibrous structural material and contaminants in changing proportions. A single tonnes-per-hour figure hides those boundaries. A defensible purchase comparison gives every supplier the same material file, output rule, site drawing and trial method.
“Biomass fuel” describes an intended outlet, not a uniform feed. Build the project file around identified source lots such as forestry residues, clean waste wood, bark and slabs, or approved agricultural woody residues. For every lot, record geometry, moisture sampling method, visible mineral contamination, storage age and mixing rule. Define the receiver's particle-size, fines, contamination and moisture acceptance criteria before estimating useful production.
Track mass to accepted fuel, oversize, recirculation, removed contamination and unresolved loss. Keep gross elapsed time beside productive grinding time so loader gaps, screen changes, discharge constraints and sampling work remain visible. Any heating, smoke or suspected self-heating in stored biomass requires the site's emergency and fire-control procedure; this worksheet does not replace it.
The purchasing team should be able to show the source of every important assumption, the party responsible for each upstream and downstream task, and the commercial consequence when the expected case is missed. Ask suppliers to mark exclusions explicitly and compare quotations against one shared material file and one accepted-output definition.
Issue the same evidence pack to every bidder: representative feed photos and measurements, annual and peak demand, required output, site layout, utilities, loader and discharge scope, working calendar, staffing, compliance constraints and the proposed acceptance test. Separate base machine, options, freight, installation, commissioning, training, initial spares and taxes instead of comparing one bundled total with another partial total.
Create low, expected and difficult-permitted cases. For each case show gross accepted output, scheduled hours, utilization, labor, energy or fuel, loader time, wear allowance, routine service, reject handling and residual disposal. Do not publish a payback period unless both the baseline cost and proposed cash flow use the same time boundary, quantity basis and outlet assumption. Treat unverified resale value, avoided disposal fee or product revenue as a labeled sensitivity—not an assured benefit.
State operating window, source shares, feed geometry, moisture method, contamination rules, required product, oversize treatment and sampling method. The biomass fuel selection guide supplies the broader purchase framework; this worksheet isolates capacity evidence.
Translate weekly or seasonal demand into accepted tonnes or documented volume per gross operating hour. Include startup, inspection, loader gaps, pile change, sampling, normal adjustments and approved cleaning. Keep peak incoming inventory separate from sustainable dispatch capcity.
Record machine model, drive, screen, wear system, discharge, mobility, loader requirement, preparation equipment, controls, training and support. Review the tub grinder range, then obtain the exact proposed configuration and permitted feed envelope.
Request material-specific test records, measurement method, gross and productive time, rejects, accepted output, screen identity and stated limitations. The throughput site-test guide helps structure comparable evidence.
List each unknown with owner, source, expected range, effect on accepted rate, control and review trigger. Use current quotations for commercial values. Do not invent fuel, wear, labour, price or universal throughput.
Send lot photographs, dimensions, source proportions, outlet specification and layout through the WDMachines contact page. The engineering product section gives a second, verified technical destination.
| Input | Record | Capacity consequence |
|---|---|---|
| Woody fraction | Daily and peak]X[�]HY�\��ܝ[������\\�]\�ܚ[�X�H��X�\�H���H�[�ۜ��X[H��X��X�Z\����������\�][���[������]�Z[X�Hܛ����\��[�[��Y������Y�[�\�H�\�Z[�X�H�\�H�\]Z\�[Y[���������X��\YZY[����]]YY][��Hܚ][��^�H[��[Z[�][ۈ�[O����]�[���Z�X��[��X�\��[][ۈ���H�Z[����[�Y\��[�\�Y�YY�������������ܘY�H�Y��\�����\\�YY�YY[�X��\Y[�]]�\X�]O��������]\�\��X[H܈�ۜ��X[H�ۙ�\�[ۈ�[��H�[��������O��X�O���[�[]HH[��[���\]Z\�[Y[����HX��\Y�]]��[���Z[��Z^Y�ZY���Y\��^X�Y[�Y��X�[�\�\��\\�]H[�\��]�\�H�\Y\���\�ۙ�H�[YH�\�ܚ\[ۜ��ܚٛ���ܙY[��ۙ][ۋ�[\[��Y]�[�ܛ���][YH��[�\�K����X[\���\\�[��\]Z\Y[�^[�]��[�\�HHܚ^�[���ܚ[�\�ݙ\��Y]����[YHY][ۘ[]Y\�[ۜ��[HHYX\�\�Y��]H[�\�[�][ۈ�[XZ[����[���܈\��ۜ��X[H��X��ڙX�����Y�\�O�[Y�[H��Y[\]Z\Y[�[\��][ۈ�܈X�ܚ[�\��\X�]H�܈�[�X\���Y[��Y[��H�^�H�ܘ�H�����˝�XX�[�\˘��Kޘ��\�\���\�Y̌�K��̌�L�M�M��M͌ � �MM��K��YȈ�[OH�X^]�Y�L N�ZY��]]ȋϏ�Y��\[ۏ�\]Z\Y[�[\��][ۈ���HH�]H[XY�HX��\�N��[�[�ۙ�Y�\�][ۈ��[�HX]�Y��\�\�[�]]�HX]\�X[[�H��[Y[�Y�X[�ٚY��\[ۏ�ٚY�\�O����[X\�H�X�ܙ���[�O��[X\�H]Y\�[ێ�X�ܚ[�\��\X�]H�܈�[�X\���Y[�O�O�X]\�X[��[�^�\�[ۜ�\�HY[�Y�YY��O�O�ܛ���[YK��X�]�H[YKX��\Y�]][��Z�X��\�HۙHܚ][���[�\�K��O�O��ۙ�Y�\�][ۋ�X\��ۙ][ۋ�Y\�[�\��\��H\��[��[Y[�\�H�X�ܙY��O�O�\��[\[ۜ�][�][ۜ�[�YX\�\�Y�\��][ۜ�\�HX�[Y�\\�][K��O�O��Y�]K�\�K\��][ۈ[�XZ[�[�[��H[���X�[ۜ��[XZ[����Y�HH�\YY��[Y[�][ۈ[��]H���Y\�\ˏ�O��[���]�Y]�H�]I��H�Y�H�����˝�XX�[�\˘��Kȏ��[]�[�\]Z\Y[�[�\X�][ۈ[��ܛX][ۏ�O�[�\�HHH�Y�H�����˝�XX�[�\˘��K�X��X�[\�\��\��\����]�[YX\�\�K]���Yܚ[�\�]��Y�]\�]K]\�ȏ��ڙX�]�Y[��H܈�X��\��\��O�O���X�Z]HX]\�X[�[K��܈H��\[Y[�\�H\]Z\Y[�ݙ\��Y]��][�H�ZQۙ��]�ܚ��YHH�Y�H�����˝���Yܚ[�\����Kȏ�ܚ^�[���ܚ[�\��O��H�ۙ�Y�\�][ۈ�X��[Y[�][ۈ��[�����\�\�[�]]�H�[\\�[�H��[Y[�Y�X[��[�[��\�Y�YYXY[�H�]K�������[Y[�HX�\�[ۈY�\�H�X[�������HH�ڙX��[H�]H\�YX]\�X[[�Y[�Y�Y\���ۙ�Y�\�][ۋ�Y\�[�\��\��H\��[��[Y[�ܛ���[���X�]�H[YKX��\Y[�]]�[K�[\\�X��ܛX[]�[��[��[�X�[ۜˈ�]H�X��Y�\�\��\�HYX\�\�Y][�Y܈\��[YY��\�\��HH[�]�YX[�[��[�Z\��[��H[��XYو�]Z[�[��ۛHHY�\��\�[�\��\�[���\�][ۜ�XZ[�[�[��H[�]X[]H��[XX��YۈH����^H�ۈ�Y�ܙHH�\�[\�\�Y�܈HXX�[�H��\\�\�ۋ�Y�]܈��X�[ۈ��[Z]Y[��� |
For teams evaluating alternate layouts for biomass fuel preparation, the horizontal wood grinder reference can support the comparison while the final decision remains tied to representative material, accepted output and a documented trial.